100000 tons/year light hydrocarbon recovery unit compressor completed load test machine
Classification:
Time: 2019-12-12
On October 3, the newly-built 100000-ton/year light hydrocarbon recovery unit overhead gas compressor C101A was tested under nitrogen condition. With the efforts and cooperation of all parties, the machine was started at 2: 40 p. m. and stopped for 2 hours after 100 load operation. This test not only tested the quality of compressor parts, the rationality of pipeline design, and accumulated operation data for later design rectification, moreover, it has trained the operation ability of new employees and the coordination ability of internal and external operations, laying a solid foundation for the next start of the device.