100000 tons/year light hydrocarbon recovery unit compressor completed load test machine
Classification:
Time: 2019-12-12
【Summary】On October 30, the overhead gas compressor C101B of the newly-built 100000-ton/year light hydrocarbon recovery unit was tested under nitrogen condition. With the efforts and cooperation of all parties, the machine was started at 9: 40 a.m. and stopped for about 6 hours at 100 load.
On October 30, the overhead gas compressor C101B of the newly-built 100000-ton/year light hydrocarbon recovery unit was tested under nitrogen condition. With the efforts and cooperation of all parties, the machine was started at 9: 40 a.m. and stopped for about 6 hours at 100 load. The completion of this test indicates that all moving equipment in the device have completed the test. The next step will be to rectify the problems found and lay the foundation for the start-up of the device.