Report on Site Construction Progress of Light Hydrocarbon Recovery Unit
Classification:
Time: 2019-12-12
【Summary】Shandong Installation Company, construction site of light hydrocarbon recovery unit, is intensively finishing the process pipeline. As of the press release, the process pipeline has been completed by 95%, and three checks and four checks are expected to be carried out next week.
Shandong Installation Company, construction site of light hydrocarbon recovery unit, is intensively finishing the process pipeline. As of the press release, the process pipeline has been completed by 95%, and three checks and four checks are expected to be carried out next week. After three checks and four determination, the pipeline with pressure test conditions is ready for pressure test. The fireproof paint in the unit has been completely painted. The compressor is ready for oil transportation this week.