Create intelligent and green tourism petrochemical enterprises

New ball tank farm construction progress tracking report


Classification:

Time: 2019-12-12

【Summary】In order to catch up with the construction period, grab the progress and make every effort to ensure the completion on schedule, all the personnel on the construction site of the new spherical tank work overtime.

In order to catch up with the construction period, grab the progress and make every effort to ensure the completion on schedule, all the personnel on the construction site of the new spherical tank work overtime. As of press release, one olefin spherical tank has been welded, one external welding has been completed, and one external welding has been completed by 30%. The external welding of the propane spherical tank TK31307 in the carbon 3 carbon 5 spherical tank area is completed, and the TK31308 welding is completed. Two ball tank materials in the propylene ball tank area are on site and are being arranged in an orderly manner.

 