Report on Construction Progress of Light Hydrocarbon Recovery Site
Classification:
Time: 2019-12-12
Shandong Installation Company, construction site of light hydrocarbon recovery unit, is intensively prefabricating and installing process pipelines. The welding capacity of the process pipeline of the device is about 32066 inches, and has been welded for more than 22000 inches. 70% of the total pipeline welding capacity has been completed. It is expected to be completed by the end of May and reach the pipeline pressure test status. At present, the fire retardant coating of the device has begun to enter the construction phase, and the fire retardant coating project is expected to be completed within 20 days. As of the time of publication, all steel structures of the light hydrocarbon recovery unit have been completed, and all the dynamic and static equipment entering the factory have been installed in place.