The company held a special docking meeting on the issue of "three checks and four fixed" for the fourth phase of new installations.


Classification:

Time:2019-12-11

【Summary】At 6:30 p. m. on September 3, a special docking meeting on the "three checks and four fixed" issue of the fourth phase of the new installation was held in the conference room on the third floor of the company. Hu Jingang, deputy general manager and chief engineer of Xinhai Group, Feng Wenhui, deputy general manager, and Huang Zhenqiang, deputy general manager, attended the meeting.

At 6:30 p. m. on September 3, a special docking meeting on the "three checks and four fixed" issue of the fourth phase of the new installation was held in the conference room on the third floor of the company. Hu Jingang, deputy general manager and chief engineer of Xinhai Group, Feng Wenhui, deputy general manager, and Huang Zhenqiang, deputy general manager, attended the meeting.

This meeting mainly focused on 376 items of design defects, construction quality and construction progress unfinished problems checked by power workshop, water workshop, sulfur workshop and engineering, production, equipment and safety disciplines in the early stage, including 131 items of new sour water stripping unit, 106 items of secondary water field and 139 items of 100 t/h gas furnace (including new water treatment).

At the meeting, the person in charge of the three sets of devices respectively explained in detail the "three checks and four determination" items sorted out by each specialty. According to the nature and actual situation of the rectification items, the company classified 376 problems, of which category a must be completed before construction starts, category B must be completed when construction starts, and category c must be completed when construction starts.

This meeting clarified the rectification tasks of the last item, implemented the responsible units and responsible persons, proposed solutions, limited the completion time of the rectification, and required all units and departments to cooperate closely, strengthen coordination, work actively, and steadily promote the "three inspections and four fixes" last item The rectification work has laid a solid foundation for the standardization, standardization, and high-quality delivery of new devices.