Construction progress report of the fifth-phase catalytic unit
- Categories:Project
- Author:
- Origin:
- Time of issue:2019-12-25
- Views:7
(Summary description)The construction of the fifth-phase catalytic unit is nearing completion, and the pipeline purge has been basically completed; three investigations
Construction progress report of the fifth-phase catalytic unit
(Summary description)The construction of the fifth-phase catalytic unit is nearing completion, and the pipeline purge has been basically completed; three investigations
- Categories:Project
- Author:
- Origin:
- Time of issue:2019-12-25
- Views:7
The construction of the fifth-phase catalytic unit is nearing completion, and the pipeline purge has been basically completed; three investigations, four determinations, and the last 470 items have been completed, and 415 gas separation MTBE devices have been completed, 102 items have been completed; 59 items have been completed. The tail items affecting the two appliances and the flue oven are basically completed. In terms of thermal insulation, 90% of the catalytic unit is completed, 93% of the gas separation MTBE unit is completed, and 78% of the alkylation unit is completed. Other closing work is in an orderly manner.
Scan the QR code to read on your phone
Phone:+86-317-5907000/5606579
Address: Middle section of Nanshugang Road, Huanghua Port, Bohai New District, Cangzhou, Hebei Province
E-mail:xinhaigroup@hbxhhgjt.com
Hebei Xinhai Holding Co., Ltd. Copyright © 2019 All rights reserved 冀ICP备19029859号