(Summary description) The 50,000 tons / year sulfur recovery unit is accelerating the construction progress according to the time point.
Report on site construction progress of 50,000 tons / year sulfur recovery unit
(Summary description) The 50,000 tons / year sulfur recovery unit is accelerating the construction progress according to the time point.
- Categories:Project
- Author:
- Origin:
- Time of issue:2019-12-25
- Views:1
The 50,000 tons / year sulfur recovery unit is accelerating the construction progress according to the time point. As of press time, the unit's civil construction is 95% completed, the equipment installation is completed 95%, the steel structure is completed 94%, and the process pipeline is currently prefabricated 76,000 inches. Chimney construction has been completed. carry out. All electrical bridges are completed, electrical piping is completed, grounding is completed 90%, lighting is completed, instrument bridges are completed 90%, conduits, instrumentation equipment are being installed.
Scan the QR code to read on your phone
Phone:+86-317-5907000/5606579
Address: Middle section of Nanshugang Road, Huanghua Port, Bohai New District, Cangzhou, Hebei Province
E-mail:xinhaigroup@hbxhhgjt.com
Hebei Xinhai Holding Co., Ltd. Copyright © 2019 All rights reserved 冀ICP备19029859号