(Summary description)As an important part of the fifth-phase project, the construction site of the 800m3 / h sewage treatment project presents a busy scene
800 cubic meters / hour sewage treatment project construction progress report
(Summary description)As an important part of the fifth-phase project, the construction site of the 800m3 / h sewage treatment project presents a busy scene
- Categories:Project
- Author:
- Origin:
- Time of issue:2019-12-25
- Views:4
As an important part of the fifth-phase project, the construction site of the 800m3 / h sewage treatment project presents a busy scene. As of press time, the biochemical pool: 75% of the steel bar binding on the pool wall was completed. The template installation is 30% complete. The steel bar and formwork of the air floatation tank have been installed. Homogeneous pond: Pond wall rafters have been poured. The oil tank liner and steel bars are being installed. The second sink pond has all been completed. In the advanced processing area, the foundation reinforcement banding has been completed. The main body of the dosing room, sludge concentration tank, dewatering machine room, and integrated pump room are under construction.
Scan the QR code to read on your phone
Phone:+86-317-5907000/5606579
Address: Middle section of Nanshugang Road, Huanghua Port, Bohai New District, Cangzhou, Hebei Province
E-mail:xinhaigroup@hbxhhgjt.com
Hebei Xinhai Holding Co., Ltd. Copyright © 2019 All rights reserved 冀ICP备19029859号